12 · The ask

Do not raise $558 million for a slide

Two cheques, never one. Holding Phase 1 is a $3.6M SME raise for Markets, Jewels and Labs. The original STAR KEY ask is $558M equity, $1.116B debt, $186M grants for a plant whose energy, offtake and resource are not yet proven. Raise development equity that buys the proofs. Paper Power at STAR KEY Energy PLC — not on AURION MARKETS.

Ask A — holding Phase 1

Pre-seed

$100k

MVP, prototypes, filings, PLC

Seed

$500k

Platform, workshop, first export lots

Series A

$3.0M

Only against an order book

Total

$3.6M

40–60% across three rounds if priced as printed

≈$7.2M if $3.6M buys 50% — rich for pre-revenue Ethiopian HoldCo unless Jewels/IP is evidenced.

Ask B — Power Phase 1 (if gates close)

Phase 1 CAPEX

$248M

50 MW PV + 20 MW geo wellfield/plant + 5 ha + interconnect

Equity (35%)

$105M

Debt (50%)

$105M

Grants (15%)

$37M

GRMF drilling + climate funds — not assumed closed

Project IRR

500.0%

Min DSCR

-0.69×

Use of Phase 1 proceeds

WorkstreamMonthsGate
3–6 deep wells + resource report (SPE/PRMS-style)18–24P90 MW ≥ 15 before power block
12-month DNI + GHI + soiling mast12CSP option lives or dies here
50 MW PV + substation bay18–24Signed PPA + IA before NTP
Pump tests, RO pilot, 5 ha greenhouse18Water licence
ESIA Category A, FPIC, land title12–18IFC PS sign-off
PPA term sheet with MoF wrapparallelNo wrap, no debt

If you insist on the 250 MW ask

Independent full-plant NPV at 10% is −$1.59B with project IRR 500.0% and min DSCR -0.16×. To clear a 1.30× DSCR you need some mix of: tariff well above $0.10, grants above 10%, leverage below 50%, or a much smaller CSP block. Use the live model in the room with the lender.

Who should be in the cap table

  • Development equity: climate PE / DFI co-invest (Proparco, FMO, Norfund, EAIF) — not a 49% cash private with 26% EEP in-kind until land and IA are real.
  • Debt: AfDB / TDB / commercial only after PPA wrap. World Bank is a policy lender to GoE, not an automatic IPP lender.
  • Grants: GRMF for wells; GCF for the adaptation (water, greenhouse) story. Bid them. Do not book them.
  • Strategic: an Ormat-class geo OEM and a CSP EPC with a completed African plant — as contractors with skin, not logos on a slide.

Conditions precedent we would write

  1. Independent resource report and 12-month on-site DNI.
  2. Executed PPA with USD capacity payment and MoF guarantee.
  3. EEP interconnection agreement and system-impact study.
  4. Land title + FPIC record + Category A ESIA.
  5. Pump test and water licence for the RO volume actually needed.
  6. Financial model audited; original 28.7% IRR retired from all decks.